Submarine power cable installation for supplying Kråmö and nearby islands in the Trosa archipelago began in March 2016, with SUAB acting as subcontractor to Vattenfall Services Nordic for Vattenfall Eldistribution. The works involved laying approximately 9.4 km of electric cable over nine stretches, constructing and installing two network stations, and preparing eight landfalls as part of a broader project to provide new electricity connections to island properties.