During 2015, the cable installation campaign for Kentish Flats Extension was completed, with two export cables and approximately 12 km of inter-array cables installed using water jetting and burial to 0.5–2 m, running from the offshore array to the Hampton Pier landfall and along the existing onshore route to Red House Farm substation; contractor support for offshore cable installation, burial, protection, termination, and testing concluded by September 2015.