Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
Energinet’s official project page "Nyt 132 kV elkabel på tværs af Gentofte Kommune til Nordhavn og Amagerværket" (KBH05, Glentegård–Nordhavn–Amagerværket) states that work to establish the new 132 kV cable connection began at the start of 2025: "I starten af 2025 begyndte arbejdet med at etablere en ny 132 kV kabelforbindelse fra Glentegård Højspændingsstation til kysten ved Hellerup og videre til Nordhavn og Amagerværket." This corresponds to the start of onshore construction for the KBH05 land cable systems. The same page’s TIDSPLAN shows preparatory works on Strandvejen from 10 February 2025 and the start of cable work in Hellerup on 17 February 2025. No later sources indicate a postponement of the onshore start, so I confirm onshore construction start in 2025, with year-level precision.