Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
In the same 7 July 2025 Energinet press release on the KBH05 subsea cable installation, the company states that the work to install the cable between Amagerværket, Nordhavn and Hellerup is expected to be completed over July and August 2025 ("Energinet forventer at kunne færdiggøre arbejdet i løbet af juli og august måned"). The seabed trench had already been prepared earlier in 2025, and the campaign is described as a focused marine operation. There is no subsequent public information indicating major delays or an additional installation season. It is therefore reasonable to treat completion of subsea cable installation for the two 132 kV KBH05 cable systems as occurring by August 2025. I record completion in August 2025 with month-level precision, acknowledging that the exact day is not specified.