Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
Danish environmental screening documents for the KBH02 project state that the land-based construction and civil works for the new 132 kV cable between Svanemølle Koblingsstation and Amagerværket were expected to start with preparatory works in September 2020 and finish in April 2021. Later expropriation documents (Dec 2022) confirm that the 132 kV cable connection was established in 2020/21, consistent with this schedule. Using September 2020 as an approximate start month for onshore construction.