Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
Cable installation for the Kårehamn offshore wind farm started during the 2012 installation campaign, when Baltic Offshore undertook turnkey supply and laying of export and array cables—two export circuits of 9 km and 5 km and around 15 inter-array cables of about 500 metres each—along with associated nearshore trenching and protection works.