Positive
Project advancing - milestone achieved
Low Impact
Minor progress or informational
By mid‑February 2023, Asso.subsea and Hellenic Cables had carried out and completed geotechnical surveys for the Kafireas II interconnection, undertaking soil and route investigations along more than 70 km of 150 kV three‑core submarine cable that links Terna Energy’s Kafireas wind farm cluster in southern Evia to the mainland grid at IPTO’s 150 kV Lavrion substation.