Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
On 21 April 2021, Terna Energy selected a joint venture of Hellenic Cables and Asso.subsea to provide the 150 kV submarine cable system for the Kafireas interconnection, linking the 330 MW Kafireas II wind farm complex in southern Evia to Greece’s mainland grid at IPTO’s 150 kV Lavrion substation in Attica. The turnkey contract, awarded following an international tender, covers the design, manufacturing, supply and installation of approximately 70 km of three‑core composite submarine cable and about 11 km of 150 kV underground onshore cable, including all accessories, joints, terminations and seabed protection works, with implementation (including offshore installation and protection) then expected to be completed by June 2022.