Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
JD-Contractor A/S began marine installation of a new 12 kV submarine transmission cable between Fur and Branden in the Limfjord on 27 March 2015, replacing and relocating one of the old transmission cables to the island of Fur after a planned directional drilling solution was abandoned due to challenging ground conditions. The work scope included route planning and survey, recovery and disposal of the old cable, loading, transport and laying of the new 3 x 150 PEX-AL cable, and burial of the new submarine cable using jetting, carried out by the near-coastal vessels S/B Victor and M/S Honte.