Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
JD-Contractor A/S completed the marine replacement and relocation of a 12 kV submarine transmission cable between Fur and Branden in the Limfjord, Denmark, following port expansion works on Fur. After route planning, survey, recovery and disposal of the old cable, and installation and burial of a new 3 x 150 PEX-AL 12 kV submarine cable using near-coastal vessels S/B Victor and M/S Honte, all tasks were finished and the cable was handed over to owner EnergiMidt on 7 April 2015.