According to Enedis and Orange's May 2022 press dossier for the Île de Groix cable replacement project, the final phase of works involves laying the new hybrid submarine cable between Ploemeur (Lomener) and Groix. The key dates section states that the subsea cable lay ("Pose du câble en mer") took place from 2–7 May 2022. This indicates that offshore cable installation started on 2 May 2022.