Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
On 18 December 2024, ABL Group was awarded a contract by TenneT to provide marine warranty survey services for the installation of three 2 GW export cable systems, including the IJmuiden Ver Beta grid connection alongside IJmuiden Ver Gamma and Nederwiek 2. ABL’s Hamburg-based team will review and approve documentation, procedures and drawings, conduct suitability surveys, and provide on-site attendance at fabrication yards, loadout sites and offshore during transportation and installation operations through to 2029.