Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
On 3 March 2023, TenneT selected NKT to deliver the 525 kV XLPE HVDC cable connections for IJmuiden Ver Beta, along with IJmuiden Ver Gamma and Nederwiek 2, as part of its 2 GW programme. NKT’s scope covers design, engineering, production, delivery, project management, and offshore, nearshore and onshore installation and jointing of the export cables landing at Maasvlakte, with onshore laying to start in 2025 and offshore laying in 2026 ahead of operation between 2028 and 2030.