Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
National Grid completed the rebuild and commissioning work at the Sellindge onshore converter station, returning the IFA interconnector to full 2 GW capacity. Contractor teams carried out installation and commissioning of HVDC valves and associated substation equipment, enabling the onshore station and its AC interfaces to be re-energised and placed back into commercial operation.