Statoil made the final investment decision to construct the 30 MW Hywind Scotland floating wind farm in early November, following the award of a marine licence by the Scottish Government in October. The FID enabled progression to construction of the five 6 MW Siemens turbines on spar-type floating foundations anchored by suction anchors at the Buchan Deep site off Peterhead.