Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
On 4 November 2022, HOPS issued an international competitive tender inviting bids for the accompanying works needed to realise the 110 kV Brač–Hvar–Korčula cable connection, which includes the Hvar–Korčula link. The notice specified an estimated contract value of HRK 25 million and a contract duration of 15 months from award.