one offshore and one onshore substation and two cable circuits consisting of 18 kilometres of subsea and 30 kilometres of land cable
Balfour Beatty Equitix Consortium reached financial close to own and operate the Humber Gateway offshore transmission link (OFTO) for 20 years. The OFTO assets comprised one offshore substation, one onshore substation and two 132 kV cable circuits, described as 18 km of subsea cable and 30 km of land cable connecting the Humber Gateway offshore wind farm to the onshore transmission grid.