Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
On 11 December 2018 Ørsted reported that termination and testing of the Hornsea Project One export cable system—comprising three high-voltage subsea export cables and a 38 km onshore cable route connecting the offshore substations and reactive compensation station to the national grid—was being completed ahead of schedule, with completion expected in the first months of 2019. This system testing related to the 467 km AC offshore export cable network that would become the Hornsea 1 OFTO transmission assets.