In December 2018, first power from the Horns Rev 3 offshore wind farm was exported to the Danish grid via Energinet.dk’s 220 kV offshore transmission system, marking the initial energisation and operational use of the Horns Rev 3 export cable and associated onshore connection to the Endrup substation.