In April 2014, Danish transmission system operator Energinet.dk awarded a high-voltage AC cable system contract to ABB and Prysmian Group for the Horns Rev 3 offshore grid connection. The scope covers a roughly 32–34 km, 220 kV three‑core polymeric insulated submarine export cable with integrated fibre optics from the offshore substation to landfall near Houstrup Strand, along with approximately 45 km of onshore HVAC cable to connect the Horns Rev 3 offshore substation and intermediate facilities to the 220 kV/400 kV transmission network at Endrup, enabling evacuation of power from the wind farm into the Danish grid.