Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
Local community site Holmöportalen published a notice dated 25 May 2020 stating that Umeå Energi Elnät "now begins" work to secure the electricity supply to Stora Fjäderägg. The notice describes replacement of about 2,000 m of 12 kV subsea cable and about 900 m of onshore cable on Holmön. It says the work starts in week 22, which begins on 25 May 2020. This is used as the onshore construction start date.