On 20 May 2020, the Dutch Council of Ministers adopted a Spring 2020 update of the Development Framework for Offshore Wind Energy that adjusted the delivery date for the offshore grid connection for Hollandse Kust (zuid) Sites I and II, based on an agreement between the permit holder and TenneT. In this updated framework, Table 3 confirms the revised offshore grid delivery date of 31 December 2021 for the Hollandse Kust Zuid Alpha 700 MW AC connection.