Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
In September 2020, DEME Group’s cable-laying vessel Living Stone completed installation of the first two export cables for the Hollandse Kust Zuid Alpha grid connection, laying two approximately 34‑kilometre 220 kV AC export cables as part of TenneT’s Hollandse Kust Zuid offshore grid linking the Alpha platform with the Dutch mainland.