Neutral
Informational - no clear directional impact
Low Impact
Minor progress or informational
By 4 March 2022, LS Cable & System had loaded the first batch of subsea export cables for the Hollandse Kust Noord and Hollandse Kust West Alpha grid connections onto Jan De Nul’s cable‑laying vessel Isaac Newton at its Donghae, South Korea, fabrication site, ahead of the first offshore installation campaign in the Netherlands. Jan De Nul also reported that its customised Moonfish cable trenching machine had successfully completed trials at Maasvlakte and was ready for deployment on the Hollandse Kust Noord export cable works.