Positive
Project advancing - milestone achieved
High Impact
Major milestone or critical setback
On 4 March 2021, CrossWind, the Shell–Eneco consortium developing the Hollandse Kust (noord) wind farm, signed grid connection and transmission agreements with transmission system operator TenneT for the Hollandse Kust Noord offshore grid connection. The agreements formalise the realisation, connection, and power transmission between the wind farm and TenneT’s 700 MW offshore platform, setting out technical standards, liabilities during construction and operation, and regulatory compliance requirements for feeding power into the Dutch high-voltage grid at Beverwijk.