Project advancing - milestone achieved
High Impact
Major milestone or critical setback
TenneT completed the Hollandse Kust Noord offshore grid connection and received a grid‑ready certificate at the end of March 2023 after final testing, confirming that the entire transmission link from the offshore transformer platform in the North Sea to the high‑voltage substation along the A9 motorway near Beverwijk is officially ready to bring green electricity ashore for the Hollandse Kust Noord wind farm.