Cable installation for the Helgoland cable began on 6 June 2009, when the cable-laying vessel Nostag 10 started work from St. Peter-Ording after multiple weather-related postponements. The vessel proceeded to lay the 30 kV subsea power and data cable towards Helgoland, installing it by jetting it approximately 1.5 metres into the sandy seabed.