Positive
Project advancing - milestone achieved
High Impact
Major milestone or critical setback
DELAYED +2yr (Apr 2026): Energinet's Hatting–Ryttergård project page (updated timeline) shows cable works start February 2026 and cable works "afsluttes og sættes i drift" in July 2027, with overall project expected in operation 2029. This replaces older commissioning expectations around 2026, so commercial operation for the cable is delayed to July 2027. --- Energinet’s 2024 geographic project list for the Midt- and East Jutland transmission network identifies the new 150 kV Hatting–Ryttergård cable as a new investment with an expected commissioning (idriftsættelse) year of 2026, indicating the planned start of full commercial operation for this interconnector in 2026.