Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
DELAYED +7mo (Apr 2026): Energinet's current Hatting–Ryttergård timeline states cable works start February 2026 and cable works "afsluttes og sættes i drift" in July 2027, later than earlier assumptions of completion by winter 2026 based on permitting material. Onshore cable installation completion is therefore delayed to July 2027. --- Onshore installation of the 150 kV cable system between Hatting and Ryttergård is planned to be carried out from spring 2026 through winter 2026, so completion of the onshore cabling is scheduled by winter 2026.