Ofgem’s cost assessment for the Gunfleet Sands transmission assets records that construction of the offshore substation, submarine export cable and associated land cable was completed and the assets were commissioned in July 2009, meaning the transmission system was fit for use in transmitting electricity from the Gunfleet Sands wind farm to the onshore grid connection at the EDF Energy substation near Clacton-on-Sea.