Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
Cable installation for the Gotland 1 HVDC submarine link began in 1953, when NKT started laying the 96 km, 100 kV submarine cable between Västervik on the Swedish mainland and Ygne on Gotland under a turnkey project for Vattenfall in the Baltic Sea, with the cable in place between the converter stations by the summer of that year.