Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
Under the framework agreement between RTE and Prysmian for the Fos Project (Golfe de Fos AO6) and Narbonnaise offshore wind connections, the specific EPCI contracts for the three 225 kV HVAC export cables for each project are expected to be called off and their terms finalised during 2026–2027. This will convert Prysmian’s framework status into fully executed project-level EPCI contracts for around 300 km of land and submarine export cables for the Fos offshore grid connection, ahead of delivery and commissioning planned for 2031–2032.