Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
Between 2011 and 2012, Gemini Wind Park’s developers (Typhoon/Van Oord) commissioned an export cable route advice and installation impact study for the Gemini export cables. The study defined the AC export cable route from the offshore wind park through the Eems estuary towards Eemshaven, focusing on avoiding shipping lanes and sensitive nature areas and on achieving sufficient burial depth in highly morphodynamic zones to minimise future exposure and maintenance risk.