Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
On 22 November 2013, the "fuseau de moindre impact" (corridor of least impact) for the Fécamp offshore wind farm’s electrical connection was validated at the sub‑prefecture in Le Havre, confirming the preferred onshore and offshore route alignment within the previously defined study area.