Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
IPTO selected Hellenic Cables as the turnkey cable contractor for the Skiathos–Evia electrical interconnection, awarding it responsibility for designing, manufacturing, testing, supplying, installing and protecting the 150 kV submarine and land cable system, including roughly 29–30 km of 150 kV submarine cable and associated land cables. The Hellenic Cables scope, which included burial of the submarine cable along its route and connection to the 150 kV transmission system at Mandoudi in Euboea, was successfully completed with the interconnection fully operational by July 2022.