By 2022, Hellenic Cables had completed its turnkey scope for the Skiathos–Euboea interconnection for IPTO, including the design, manufacturing, testing, supply, installation and full protection of approximately 30 km of 150 kV submarine cable and associated land cables, connecting Skiathos via a buried subsea route at depths of around 200 m to the 150 kV national transmission system at Mandoudi in Euboea.