Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
On 23 February 2022, the Croatian Transmission System Operator (HOPS), with KONČAR – Engineering as contractor, started laying the first 7,300‑metre 110 kV submarine cable between Postira on the island of Brač and Dugi Rat on the mainland, marking the beginning of the Dugi Rat – Postira interconnector cable replacement. The works form the first phase of a strategic project to replace aging 110 kV submarine cables on Adriatic islands, financed through the National Recovery and Resilience Plan to secure reliable electricity supply.