Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
Offshore construction of EnBW N-12.3 expected to commence around 2030, anchored to the LanWin5 (NOR-13-1) grid system commissioning timeline of 2032 Q3 per FEP 2025 amendment. German offshore wind projects typically begin offshore installation 2 years prior to grid commissioning; exact start depends on FID timing, supplier selection (turbines, foundations, vessels) and pre-construction surveys.