Positive
Project advancing - milestone achieved
Low Impact
Minor progress or informational
NjordIC’s UXO consultancy contract announcement for the Doordewind 1 & 2 Grid Connection System explains that the scope covers full‑scope UXO consultancy, including survey preparation, supervision and quality control of UXO surveys, data analysis and delivery of Master Target Lists, with project milestones planned ahead of 31 December 2026 deadlines. The article states that NjordIC’s Remote Data Centre will support timely delivery of milestones before the end‑2026 deadline, implying that completion of the UXO survey and related consultancy work is targeted by the end of 2026. No later date is reported, so the original end‑2026 projection remains valid. I therefore confirm the UXO survey completion as aligned with the year‑end 2026 schedule.