Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
In approximately October 2024, TenneT awarded NjordIC the UXO Consultancy Services Contract for the Doordewind 1 & 2 Grid Connection System, which includes the 2 GW Doordewind 2 offshore grid link. NjordIC will act as independent UXO consultant and CS-OOO A-scope holder for the approximately 112-kilometre offshore and 14-kilometre Wadden Sea export cable route, providing survey preparation, supervision and quality control of UXO surveys, geophysical data analysis, and delivery of Master Target Lists to enable safe cable installation ahead of 31 December 2026 deadlines.