Positive
Project advancing - milestone achieved
Low Impact
Minor progress or informational
NextGeo’s December 16, 2024 press release on its €43 million contract with TenneT for the Doordewind marine route survey states that operational activities, including both geophysical investigations and geotechnical sampling, are scheduled between the end of Q1 and Q4 2025. Their 1H 2025 results presentation lists Doordewind 1&2 Marine Route Survey with combined geophysical, geotechnical and UXO survey scope as one of the main projects in the first half of 2025, confirming execution in 2025. No public sources indicate that the Doordewind geotechnical campaign extended into 2026, so it is reasonable to treat the geotechnical investigations as completed by late Q4 2025. I therefore use an approximate completion date in late December 2025, in line with the planned Q4 2025 window.