Positive
Project advancing - milestone achieved
Low Impact
Minor progress or informational
NextGeo was awarded a €43 million contract by TenneT for extensive geophysical and geotechnical Marine Route Survey activities for the Doordewind wind area (including Doordewind 1 & 2 grid connections), with operational activities scheduled between the end of Q1 and Q4 2025. NextGeo’s 1H 2025 results presentation lists "Doordewind 1&2" Marine Route Survey (geophysical, geotechnical and UXO survey) among its main projects in the first half of 2025, confirming that offshore survey operations had started by mid-2025. Using an approximate start date in early Q2 2025, consistent with the planned start at end-Q1 2025.