Neutral
Informational - no clear directional impact
Low Impact
Minor progress or informational
At the end of 2021, the Netherlands Ministry of Economic Affairs and Climate Policy initiated the Offshore Wind Connection – Eemshaven Programme (PAWOZ‑Eemshaven), a programme‑based approach to investigate landfall options and resolve major spatial challenges for grid connection routes to Eemshaven, including those for Doordewind Wind Farm Site I and its planned 2 GW HVDC grid connection (Doordewind 1). The programme examines route alternatives across the Wadden Sea and the final approach to Eemshaven, and later documents note that landings for Doordewind Site I remain under investigation within PAWOZ, leaving the delivery date of the landfall uncertain.