Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
In February 2019, two 8.5 km long Nexans AXCLTV 24 kV subsea power cables were laid in parallel from a switchgear near the shore at Billdal, with the first 250 metres installed in pipes through a horizontally drilled hole under the seabed, and then pulled out across the seabed to Donsö in Gothenburg’s southern archipelago, completing the subsea cable installation for the new electricity supply link to the island. This work forms part of Ellevio’s programme to reinforce the reliability of the electricity network to the southern Gothenburg archipelago.