DELAYED +11mo (Apr 2026): Amprion’s DolWin4/BorWin4 project progress page and press releases state that converter construction in Lingen runs until the second half of 2027 and that commissioning (Inbetriebnahme) of the offshore connections is planned for the end of 2028. The NEP 2037/2045 and Amprion earlier communications keep the commissioning year at 2028 but do not support an early‑2028 date. Given this, the previous projection of 2028‑01‑01 for full commercial operation is unrealistically early; adjusting to late 2028 to align with the stated end‑2028 commissioning window. --- DolWin4 target commissioning 2028 per NEP 2037/2045 (2025) Startnetz Table 20.