Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
Under its turnkey HVDC Light contract for DolWin1, ABB was selected to design, manufacture and install the project’s HVDC Light cable system for TenneT, comprising two 75 km submarine cables, two 90 km underground HVDC cables and a 7.5 km underground AC cable linking the DolWin alpha offshore converter platform with the Dörpen-West onshore substation.