The DolWin1 HVDC offshore grid connection, including the onshore HVDC converter station at Dörpen West/Heede, was commissioned in 2015. This brought into operational service the ±320 kV, 800 MW HVDC Light link transmitting power from the DolWin alpha offshore converter platform via a 75 km subsea cable and 90 km land cable into the German transmission grid.
DolWin1 grid connection system commissioned and operational.
On 2 June 2011, TenneT TSO GmbH awarded Norddeutsche Seekabelwerke (NSW) a major order to supply and install two 13 km, 155 kV AC submarine transmission cables to connect the MEG 1 offshore transformer platform to TenneT’s DolWin alpha converter station about 75 km off the German coast, providing the network link that forms part of the 800 MW DolWin1 grid connection from the offshore wind farms to the Dörpen West converter station.
Transmission system operator Transpower/TenneT awarded ABB a turnkey HVDC Light contract for the DolWin1 offshore grid connection in the German North Sea, making ABB the supplier of the ±320 kV VSC converter stations, including the DolWin alpha offshore platform and the onshore converter station at Dörpen West, for an 800 MW link connecting the Borkum West II wind farm cluster to the German high-voltage grid.
Under its turnkey HVDC Light contract for DolWin1, ABB was selected to design, manufacture and install the project’s HVDC Light cable system for TenneT, comprising two 75 km submarine cables, two 90 km underground HVDC cables and a 7.5 km underground AC cable linking the DolWin alpha offshore converter platform with the Dörpen-West onshore substation.
ABB successfully energised its HVDC Light onshore converter station at the Dörpen West substation, completing the crucial onshore element of TenneT’s DolWin1 offshore transmission project in the German North Sea. This commissioning of the Dörpen West converter station enables the ±320 kV HVDC link from the DolWin alpha offshore converter platform to feed power into the German high-voltage grid.
Within the DolWin1 offshore transmission project, completion of the export cable connection from the offshore installations to shore was scheduled to occur during the third quarter (Q3), so that the grid link would be ready in time to transmit power from the 200 MW first phase of Trianel’s Borkum West 2 wind farm.