Cyclades Interconnection Phase D : Milos - Folegandros
Approximately February 2025
Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
Greek press and IPTO communications show that the high‑voltage submarine cable interconnections Milos–Folegandros and Folegandros–Thira had been fully laid by February 2025. Since cable laying must have started before completion and no separate start date is published, we treat this milestone as having been achieved by February 2025, using that month as an approximate start timeframe.