Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
In 2018, IPTO (ADMIE) awarded a contract to the Hellenic Cables–Fulgor consortium to design, manufacture, install, protect, terminate and test about 52 km of 150 kV AC three-core submarine cables with XLPE insulation and integrated fibre optics for Cyclades Phase B, covering the Paros–Naxos and Naxos–Mykonos interconnections and thereby including the Naxos–Paros link.