Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
By the end of June 2018, IPTO selected the Hellenic Cables SA – Fulgor SA consortium to supply and install the high‑voltage submarine cables for Cyclades Interconnection Phase B, including the 150 kV AC three‑core submarine link between Naxos and Mykonos (and the parallel Paros–Naxos link). Contracts for these cable works, covering design, manufacturing, installation, protection, termination and testing of about 52 km of cable, were then signed in July and August 2018.